<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=192888919167017&amp;ev=PageView&amp;noscript=1">
Friday,  April 19 , 2024

Linkedin Pinterest
News / Northwest

Seattle tunnel contractors say digging to resume by Nov. 23

The Columbian
Published: July 17, 2015, 12:00am

SEATTLE — Seattle’s broken-down tunnel-boring machine is slated to start digging again by the end of November and should reach the north end of downtown in about a year, officials said Friday.

But drivers wouldn’t be traveling through the tunnel until 2018 — almost three years later than originally planned, said Todd Trepanier, the state’s program manager. And Trepanier said the state isn’t able to verify the contractor’s schedule.

The state’s contractor — Seattle Tunnel Partners — released the updated schedule and led members of the media on a tour of what would someday be a double-decker roadway, replacing the Alaskan Way Viaduct after it was damaged in the magnitude-6.8 Nisqually earthquake in 2001.

Although the machine isn’t digging, crews have continued to build other parts of the overall $3.1 billion replacement project’s entry and exit sites.

In addition to delays, critics worry about potential cost overruns. The state has emphasized that under the contract, Seattle Tunnel Partners would be on the hook for extra costs. But others expect any disputes to be settled in the courts.

Bertha, the tunnel-borer, broke down in December 2013 and crews spent much of 2014 digging a pit to access the front of the machine so the cutter head could be repaired.

Seattle Tunnel Partners pulled the machine out of the ground in March, and said in a statement Friday that they began installing a new main bearing on the machine this week.

Repairs are scheduled to be completed in the fall, said project manager Chris Dixon, explaining that crews will use the time “to ensure the repairs are done right.”

Since lifting the front of the machine out of the pit, the contractor has fixed broken parts but also made enhancements, state officials said, including a new seal system to protect the bearing, more reinforcing steel, a new monitoring system and upgrades to the soil-conditioning system to prevent clogging.

The new schedule has crews lowering the cutter head into the access pit and attaching it to the tunnel boring machine on Aug. 15. They’ll spend months reattaching wires, hoses, cables, and pipes before running a series of performance tests by Nov. 21, and start building the tunnel again on Nov. 23, according to the schedule chart.

Loading...