Long outage scheduled at Hanford nuclear plant

The Columbian
Published: March 15, 2011, 12:00am

RICHLAND, Wash. (AP) — The only nuclear power plant in Washington is shutting down next month for its longest outage ever — about 80 days.

In addition to a refueling the Columbia Generating Station, which usually takes a little more than a month every other year, workers will be replacing the condenser, which turns steam back into water for reuse.

The Tri-City Herald reports Energy Northwest is hiring about 1,800 temporary workers for the $152 million project. The upgrade and other work will add about 12 megawatts to the 1,150-megawatt plant.

When it shuts down on April 6 the plant will have been running a record 486 consecutive days.

___

Information from: Tri-City Herald, http://www.tri-cityherald.com

Support local journalism

Your tax-deductible donation to The Columbian’s Community Funded Journalism program will contribute to better local reporting on key issues, including homelessness, housing, transportation and the environment. Reporters will focus on narrative, investigative and data-driven storytelling.

Local journalism needs your help. It’s an essential part of a healthy community and a healthy democracy.

Community Funded Journalism logo
Loading...