$3.9M OK’d for Packwood sewer work

Lewis County hopes project will be done by 2024

By Isabel Vander Stoep, The Chronicle
Published: March 2, 2023, 8:02pm

CENTRALIA — Packwood residents can celebrate one small victory after the county commissioners on Tuesday approved a $3.9 million contract to begin the architecture of sewer systems in Lewis County’s easternmost community.

The contract is with HDR Engineering Inc.

The sewer has been a decadeslong desire for many in the town. State Rep. Peter Abbarno, R-Centralia, was able to secure $8 million in state appropriations for the work in 2021. Funds approved on Tuesday come from that appropriation. When those dollars were approved, Lewis County officials said work on the project could be completed as soon as 2024.

County Manager Erik Martin said he anticipates the consultant’s first steps will include determining scope, schedule and budget. While he said the county is not certain yet of the time or if the $8 million appropriation will cover the entire project, those questions should be answered in the coming months.